The Contract involves the construction of 175m of 1050 diameter stormwater pipe to replace the existing box culvert under 162 West Street, 450mm pipe on West street and 900mm pipe in Victoria Park. The Contract covers the construction of 1050mm diameter concrete pipes laid from 162 West Street, through West Street and into Victoria Park open drain, installation of 1500mm, 1800mm and 2300mm Stormwater manhole and installation of 1050mm diameter headwall both at the inlet and outlet.
The contract was awarded to B.Bullocks (2009) Limited with a contract duration of 8 weeks. Work is expected to be completed by April 2020.